Skip to content
USPS Cape Coral — Commercial Remodel

Commercial Remodel

USPS Cape Coral — Commercial Remodel

C&S Plumbing is the plumbing contractor on a commercial remodel of a U.S. Postal Service facility in Cape Coral, built by Engelke Construction Solutions, LLC. Scope covers full plumbing demolition, a water repipe, new rough-in, and fixture trim.

Phase photos below run from demo through trim as the remodel progresses.

Case study

How we approached this project

Scope in short

For Engelke Construction Solutions, the general contractor, C&S demolished the existing plumbing, replaced the building's water lines, roughed in the remodeled layout and trimmed out the restrooms.

The water repipe

The old copper supply lines were corroded at their soldered joints. The new copper water line runs overhead, above the ceiling grid, joined with press fittings and installed from a scissor lift.

Finished fixtures

The restrooms are trimmed out with wall-hung toilets and a urinal on flushometer valves and wall-hung lavatories with chrome faucets.

Scope of work

  • Plumbing demolition
  • Whole-building water repipe
  • Rough-in
  • Fixture trim-out

Materials installed

  • Copper water line with press fittings
  • Wall-hung toilets and urinal with flushometer valves
  • Wall-hung lavatories
Client
Engelke Construction Solutions, LLC
Timeline
In Progress
Cost
On Request
Location
Cape Coral, FL
Photos
23

Phase 1 of 4

Demolition

Existing plumbing demolished and removed to prep the facility for the remodel.

Photo 01 / 07

  • Restroom demo with the floor-mount toilet pulled, closet flange exposed, lavatory removed and ADA grab bars in place
  • Demo with wall tile chased open, old supply stubs exposed and the slab cut for new below-slab drains
  • Gutted USPS Cape Coral restroom with fixtures pulled, tile chased to the block and slab trenched for drains
  • Wall-hung urinals and tank toilet pulled and staged during demo, with capped supply stubs and the slab opened
  • Demo in progress with lavatories removed, wall chases opened and a slab trench cut along the block wall
  • Tile chased open exposing old supply stubs above a slab cut and the existing PVC drain stub
  • Block wall chase opened at the lavatory wall showing existing PVC vent and supply lines above the trench

Phase 2 of 4

Water Repipe

New water distribution piping run to replace the building's aging supply lines.

Photo 01 / 07

  • Copper press fittings, elbows, tees and reducers laid out on the tile floor ahead of the water repipe
  • Copper pipe lengths and press fittings staged on the floor for the USPS Cape Coral water repipe
  • Corroded copper supply lines with green verdigris at soldered tees and a ball valve, replaced in the repipe
  • Brass ball valve on the copper water service stub-up with a copper sleeve through the exterior block wall
  • Plumber on a scissor lift running copper water main above the ceiling grid under the metal roof deck
  • Overhead copper supply line being pressed into place above the suspended ceiling grid from a scissor lift
  • Plumber on a scissor lift installing overhead copper water line above the ceiling grid at the USPS facility

Phase 3 of 4

Rough-In

New drain, waste, vent, and supply rough-in for the remodeled layout.

Photo 01 / 07

  • Copper hot and cold stub-outs with a PVC drain stub-out through mold-resistant drywall for a wall-hung lavatory
  • Two slab cuts patched with fresh concrete after below-slab drain work, marked with orange layout paint
  • Lavatory bank rough-in with copper supply stub-outs and PVC drain stub-outs capped through mold-resistant drywall
  • Close-up of copper hot and cold stub-outs and a PVC drain stub-out roughed for a wall-hung lavatory
  • In-wall rough on furred block wall with copper stub-outs on blocking, PVC drain with sanitary tee and cleanout
  • PVC DWV risers with sanitary tees and copper stub-outs on the chased block wall above the slab trench
  • Copper stub-outs, PVC drain stubs and wood blocking for wall-hung fixtures, floor drain set in the open slab

Phase 4 of 4

Trim-Out

Finish fixtures set and final connections made.

Photo 01 / 02

  • Wall-hung toilets with chrome flushometer valves and wall-hung lavatories trimmed out in the USPS Cape Coral restroom
  • Wall-hung urinal, wall-hung toilet and two lavatories with chrome faucets and flushometers trimmed out above a floor drain

Ready to Get Started?

Whether it's an emergency or a planned project, our team is ready to deliver the quality and reliability that's made us Southwest Florida's most trusted plumbing company.

Free estimates · No hidden fees · Satisfaction guaranteed

CallTextRequest